Current:Home > NewsMassachusetts budget approval allows utilities to recoup added cost of hydropower corridor -Wealth Axis Pro
Massachusetts budget approval allows utilities to recoup added cost of hydropower corridor
View
Date:2025-04-15 20:50:32
PORTLAND, Maine (AP) — A budget signed by Massachusetts Gov. Maura Healey this week will allow utilities to raise rates to make up for hundreds of millions of dollars in additional costs to complete a transmission line to bring Canadian hydropower to the New England electricity grid.
The head of Central Maine Power Co.'s corporate parent Avangrid has said the cost of the $1 billion project grew to $1.5 billion as litigation delayed construction and inflation caused prices to creep upward.
Legislation included the supplemental budget adopted Monday allows transmission service agreements to be renegotiated and additional costs to be passed along to Massachusetts ratepayers to cover the added costs.
Avangrid provided the increased costs to Massachusetts’ electricity distribution companies to adjust the rate in the parties’ transmission services agreements, which would be subject to Department of Public Utilities review and approval, Avangrid spokesperson Leo Rosales said in a statement Tuesday.
He praised Healey and lawmakers for taking action to “deliver this critical project and needed clean power to benefit the entire New England region.”
Avangrid partnered with Hydro-Quebec on the New England Clean Energy Connect to supply 1,200 megawatts of hydropower to meet green energy goals in Massachusetts. That would be enough electricity to power about a million homes.
The 145-mile (233-kilometer) transmission line will stretch from Lewiston, Maine, to the Canadian border.
It received all regulatory approvals but was plagued by delays, litigation and a referendum in which https://apnews.com/article/election-2021-maine-hydropower-line-54dea1a948e9fc57a667280707cddeb7
It was allowed to move forward after a Maine jury concluded that the developers had a constitutional right to proceed despite the referendum.
Construction resumed in August on a transmission hub that’s critical to the project in Lewiston. But it’s unclear when other work will restart.
Workers had already begun removing trees and setting utility poles on a disputed portion of the project, a new 53-mile (85-kilometer) section cut through the woods in western Maine, before the project was put on hold.
The project was envisioned to meet Massachusetts’ clean energy goals, and the cost is fully borne by ratepayers in that state.
However, supporters say electricity would lower energy costs across New England as well as reduce carbon pollution.
veryGood! (19)
Related
- IRS recovers $4.7 billion in back taxes and braces for cuts with Trump and GOP in power
- Longtime umpire Ángel Hernández retires. He unsuccessfully sued MLB for racial discrimination
- Son of Sam serial killer David Berkowitz denied parole after 12th board appearance
- RHOC's Heather Dubrow Teases Shannon Beador, Alexis Bellino, John Janssen Love Triangle Drama
- McConnell absent from Senate on Thursday as he recovers from fall in Capitol
- Alabama Barker Shares Her Dear Aunt Has Been Diagnosed With Brain Cancer
- Boston Celtics sweep Indiana Pacers, return to NBA Finals for second time in three years
- Adam Lambert talks Pride, announces new EP 'Afters'
- How to watch the 'Blue Bloods' Season 14 finale: Final episode premiere date, cast
- New Jersey and wind farm developer Orsted settle claims for $125M over scrapped offshore projects
Ranking
- Working Well: When holidays present rude customers, taking breaks and the high road preserve peace
- Virginia-based tech firm settles allegations over whites-only job listing
- What is Manhattanhenge and when can you see it?
- University of Florida employee, students implicated in illegal plot to ship drugs, toxins to China
- Apple iOS 18.2: What to know about top features, including Genmoji, AI updates
- Alabama coach Kalen DeBoer showed why he isn't Nick Saban and that's a good thing
- Israel airstrike in Rafah kills dozens as Netanyahu acknowledges tragic mishap
- US consumer confidence rises in May after three months of declines
Recommendation
Dick Vitale announces he is cancer free: 'Santa Claus came early'
California evangelical seminary ponders changes that would make it more welcoming to LGBTQ students
Volkswagen, Mazda, Lamborghini, Kia among 94,000 vehicles recalled: Check car recalls here
What is matcha? What to know about the green drink taking over coffeeshops.
B.A. Parker is learning the banjo
Body found after person went missing trying to swim from Virginia to Maryland, officials say
Four years after George Floyd's murder, what's changed? | The Excerpt
Rick Carlisle shares story about how Bill Walton secured all-access Grateful Dead passes